Name of project: Provision of solar street lights for residents of ebedebiri in sagbama LGA
Location: Bayelsa
Amount wasted: ₦93,800,000
Year: 2016

Gov authority involved: Federal Government

Main Officials involved: NDDC

Reason for abandonment: 240 million naira was budgeted. Of this amount, 40 million was released in 2016 while 53.8 million naira was released from the 2015 appropriations act bringing the whole amount to 93.8 million naira. The street lights were installed but not working.